RACI model


A Responsibility Assignment Matrix (RAM), (also known as RACI matrix or Linear Responsibility Chart (LRC)), describes the participation by various roles in completing tasks or deliverables for a project or business process. It is especially useful in clarifying roles and responsibilities in cross-functional/departmental projects and processes.

The matrix is typically created with a vertical axis (left-hand column) of tasks (e.g., from a work breakdown structure WBS) or deliverables (e.g., from a product breakdown structure PBS), and a horizontal axis (top row) of roles (e.g., from an organizational chart) – as illustrated in the image of an example responsibility assignment (or RACI) matrix.

There is a distinction between a role and individually identified people: a role is a descriptor of an associated set of tasks; may be performed by many people; and one person can perform many roles. For example, an organisation may have 10 people who can perform the role of project manager, although traditionally each project only has one project manager at any one time; and a person who is able to perform the role of project manager may also be able to perform the role of business analyst and tester.

The responsibility assignment matrix is commonly known as a RACI model. RACI (pronounced /ˈreɪsi/) is an acronym derived from the four key responsibilities most typically used:

Responsible
Those who do the work to achieve the task. There is typically one role with a participation type of Responsible, although others can be delegated to assist in the work required (see also RASCI below for separately identifying those who participate in a supporting role).

Accountable (also Approver or final Approving authority)
Those who are ultimately accountable for the correct and thorough completion of the deliverable or task, and the one to whom Responsible is accountable. In other words, an Accountable must sign off (Approve) on work that Responsible provides. There must be only one Accountable specified for each task or deliverable.

Consulted
Those whose opinions are sought; and with whom there is two-way communication.

Informed
Those who are kept up-to-date on progress, often only on completion of the task or deliverable; and with whom there is just one-way communication.

Very often the role that is Accountable for a task or deliverable may also be Responsible for completing it (indicated on the matrix by the task or deliverable having a role Accountable for it, but no role Responsible for its completion, i.e. it is implied). Outside of this exception, it is generally recommended that each role in the project or process for each task receive, at most, just one of the participation types. Where more than one participation type is shown, this generally implies that participation has not yet been fully resolved, which can impede the value of this technique in clarifying the participation of each role on each task.

Because of the pattern of the coloring on the chart, it is also known as a Navajo blanket.

Written by: Charen Smith

We also suggest this relevant article if you have time: Value Stream Mapping (VSM)

Some other similar articles


Tagged as , , , , , , + Categorized as Economy articles, Ladership & Management

Leave a Reply